Astronomy News
The Chang’e-7 lunar exploration mission has been forced to postpone its launch to 2027
China has announced a postponement in the Long March 5 Y14 launch, the rocket booster that was meant to deliver Chang’e-7 spacecraft along with Thailand’s science payload: the CE-7 MATCH to the Moon. The official announcement only states that the mission “could no longer meet the conditions for launch”: an abrupt event in the Chang’e program, as the Chang’e missions 1-6 all launched on schedule.
Shackleton Crater Cr. NASA
So why has the launch of the Chang’e 7 mission, which Thailand is taking part in, been delayed all the way to next year?
Launch Window
Typically, planetary exploration missions have a “launch window”, a crucial period in which the positions of earth and the target enable the spacecraft to travel efficiently while minimizing fuel consumption. Miss that window by mere days, and the intended fuel may no longer be sufficient, forcing a wait for the next launch window. Take the case of Mars, where the window occurs only when Mars sits roughly 44-47 degrees ahead of Earth in its orbit. This allows for the spacecraft to catch up with mars as it travels in an elliptical orbit to reach the orbit of Mars. Missing this window could mean waiting another 2 years before the next one arrives.
Fortunately, in the case of lunar travel, the moon’s fairly constant distance from earth allows less emphasis on the orbital position. Instead of the alignment in the orbit, Lunar transfer windows rely more on the Moon’s orbital plane crossing into the Earth’s equatorial plane. This occurs more frequently and Lunar launch window often occurs every month.
Another factor to be considered is the lunar “phase”. Taking 27.3 days, the moon’s rotation around its axis means that any given point on the lunar surface will spend 357 hours in the darkness, in which temperatures fall as low as -173 Celsius: cold enough for metal components to shrink and break off from circuit boards. Lunar missions often aim to land at the site during the daytime period due to a night spanning 14 days hindering solar panels to generate electricity, forcing most missions to meet their end when night falls.
Shackleton Crater
The Chang’e 7 mission is ambitious in that it will be the first to land inside Shackleton Crater, near the Moon’s south pole, in which sunlight has almost never reached the floor of the crater for the past 2 billion years, and the temperature stays at a constant -173 Celsius. Such extreme cold leads to a very probable discovery of water, since any ice delivered there from comets were likely preserved. The aimed landing site is the crater rim, an area that receives sunlight almost year-long, while the hopper can make short jumps from the rim into the dark crater floor, and back out, with the goal of searching for ice.
Such a discovery would certainly enhance the feasibility of establishing a human settlement on the lunar surface in the future.
The Moon’s axis being tilted by 1.53 degrees means little seasonal change, which entails sunlight reaching the landing site only on a few occasions over the course of a whole year. While it is a possibility that the lander could make use of sunlight at the crater rim, studying the Shackleton crater surface likely requires instances where sunlight slants onto the floor. Furthermore, being the first Chang’e mission heading for the Lunar poles, Chang’e 7 mission has very little information about the landing site, thus needing at least three months to gather landing-site data from orbit. Polar orbit requires an even stricter launch window to align the spacecraft path with the orbital plane. With so many factors at play, the mission’s strict requirements of a few meter landing precision across rugged terrain under faint lighting means that the next available Launch window will not happen in 2026.
CE-7 MATCH
Although Thailand’s CE-7 MATCH instrument, designed to measure cosmic radiation in orbit around the Moon, is not directly connected to the landing operation, both are components of the Chang’e-7 mission. Therefore, the start of Thailand’s space-weather measurement mission will have to wait a bit further.
As of 25 August 2026, there is still no official schedule for the next launch. Chinese authorities have merely stated that “there will be no Chang’e 7 launch this year.” But for such a long-term postponement, the rocket has already been taken off the launch pad, the spacecraft will now be put into storage, instruments disassembled, and another round of equipment checks and assembly will need to be completed before the next launch attempt.
With a lengthy wait, some scientific instruments may face service-life issues, specifically those with an RHU (Radioisotope Heating Unit), which relies on the radioisotope Pu-238 to produce heat to resist equipment from extreme cold. With time, the radioactive material decays, reducing the RHU’s efficiency. That said, as Pu-238 has a half-life of more than 87.7 years, a one-year-long delay amounts to an efficiency loss of less than 1%.
As for the Thai CE-7 MATCH instrument, its power is drawn from the orbiter's solar panels with no battery component, therefore it faces no service-life constraint. Thailand’s mission itself, a long-term cosmic-radiation measurement in lunar orbit, can still fulfill its mission by the time the next launch happens.
But for now, Thailand’s first attempt at reaching the Moon will have to wait just a little bit longer.
Text: Poruetai Nitiwarangkul